An update from Cllr John Hacking.

Works are progressing on the Cycleway and the last two quadrants at the Four Banks. We are expect work to be completed at this junction by the end of July.

A collapsed drain has been found at the junction, which goes directly across the main stretch of carriageway. While not as serious as the void found earlier on in the project, the issue needs to be fixed in order to progress the works. The maintenance team will therefore carry out repairs on night shifts, under an emergency Temporary Traffic Regulation Order – 7 and 8 June, between 7.30pm and midnight.

The Highways Team is working with Environmental Health to reduce noise and disruption to residents. Please look out for Manchester City Council communications on social media or local radio for further updates.